ERAM SHAHR DG Power Plant: Operation phase begins

After initial commissioning tests, the ERAM SHAHR 10 MW DG Power Plant, achieves full commercial operation.

The plant situated in a 63kV/20kV substation in eastern Tehran, uses 10 gas fired gen-sets made by GUASCOR, each with rated capacity of 1025 kWe with an overall capacity equal to 10 MWe.

After increasing the voltage to 20kV, generated electricity is fed to national grid through ERAM SHAHR substation feeders.

The whole 24/7 operation program is conducted by TanirTech operation team, settled in the power plant. The Plant is also connected to TanirTech`s Remote Monitoring and Control Center (RMCC).

+ See ERAM SHAHR Substation in Projects Section for more details...

eramshahr1 eramshahr2 eramshahr3






















TanirTech News

2015/03/18, 12:42
milad-tower-cchpMilad Tower CCHP Milad Tower CHP plant is the first project of CCHP in Tehran which has been completed by Tanir group in...
2014/01/25, 12:42
chp-system-commissioning-and-test-in-hekmat-power-plantCHP System Commissioning and Test in Hekmat Power Plant Along with the completion the heat consumers of Hekmat complex, heat recovering system was...
2012/12/12, 09:07
eramshahr-operation-enERAM SHAHR DG Power Plant: Operation phase begins After initial commissioning tests, the ERAM SHAHR 10 MW DG Power Plant, achieves full commercial...

Cogeneration News

On-site Power News

| Copyright © 2013 TanirTech Co. | Mozilla FireFox is recommand for a better experience of this website | Designed By Bardia Afzar Parse |